Total Percentage Completed - 30.05% 51.00% - Site Mobilization 95.82% - Enabling Works 94.78% - Piling and Foundation 86.49% - Sub-structure 32.16% - Super Structure 1.65% - Internal Works 0.58% - External Envelope 8.55% - Building Services 0% - Internal Finishes 0% - External Works 0% - Infrastructure Overall status of this project is on track and completion is due by Q4 - 2020. 447 viewsDubaiBTC @apindubai, 11:27